An offer calculation is the pre-calculation before acceptance of the order: The price that an enterprise offers is generated from material, processing time, one-off costs, overhead costs and profit. For CNC parts, the cutting volume first becomes machine time, then increases, discount and discount lead to the offer price.
Formulas
tH = V ÷ (Q × η) + tNProcessing time
Machining volume V, time machining volume Q, utilization degree η and side time tN.
KM = tH ÷ 60 × MaschinenstundensatzMachinery costs
The calculated processing time is evaluated with the operating rate.
SK = (Einzelkosten + Rüst-/Einmalkosten je Teil) × (1 + GK)Cost of production
Overheads are added to the full cost base.
AP = SK ÷ (1 − Marge)Tender price
The margin is calculated from the selling price, not as a simple surcharge.
Milling part with 48 cm³ cutting volume, batch size 25
Q = 24 cm³/min, 70% usage, 3 min side time, 85 €/h machine, 18 min setup and 120 € programming.
- Main and secondary time = 48 ÷ (24 × 0.70) + 35,86 min
- Machine costs = 5.86 ÷ 60 × 85 €8,30 €
- Set-up percentage = 18 ÷ 60 × 85 € ÷ 251,02 €
- Programming share = 120 € ÷ 254,80 €
- Material, tools and testing16,50 €
ResultThe technical cost base is ahead of overheads and margin of 30.62 € per part.
The calculator also shows overhead costs, cost, margin, unit price and order value. For scaled prices, simply change the lot size.
Which costs belong in a CNC precalculation
A meaningful input sequence separates technical quantities, direct costs and operational surcharges.
| Cost block | Typical content | Reference |
|---|---|---|
| Technical time | Main time, tool change, measurement, handling | Minutes per part |
| Material | Raw material, cutting, trimming | Euro per part |
| Tools | Stock share, special tool | Euro per part |
| Quality / external | Test, certificates, heat and surface | Euro per part |
| Setup / Programming | Machine setup, CAM, device | Unique per lot |
| General expenses/margin | Administration, distribution, risk, result | Percentage |
Operational calculation schemes can distribute surcharges differently. It is crucial that no cost block is set twice or not at all.
What is an offer calculation?
The offer calculation is a preliminary calculation: it arises before an order is accepted and answers the question at which price a company can offer a part. In part production it usually follows the surcharge calculation. Individual costs such as material and machine time are directly attributed to the part, overhead costs are added as a percentage. From the cost of the cost are with profit, customer account and customer discount cash sale price, target selling price and list price.
Calculation scheme up to the offer price
The milling part from the example below, per piece for lot size 25. Assumed: 18 % overhead costs, 12 % margin from the selling price, 2 % customer account and 5 % customer discount.
| Stage | Calculating path | Per piece |
|---|---|---|
| Material, tools, testing | Unit cost | 16,50 € |
| Machinery costs | Unit time ÷ 60 × hourly rate | 8,30 € |
| Equipment and programming part | One-off cost ÷ Lot size | 5,82 € |
| Cost base | Total | 30,62 € |
| General expenses | Cost base × 18 % | 5,51 € |
| Cost of production | Cost base + overheads | 36,13 € |
| Profit | Cash selling price – cost of production | 4,93 € |
| Cash selling price | Cost of production (1–12 %) | 41,06 € |
| Customer account | Target selling price × 2 % | 0,84 € |
| Target selling price | Cash selling price ÷ (1 – 2 %) | 41,89 € |
| Customer discount | List price × 5 % | 2,20 € |
| Offer price (list price, net) | Target selling price ÷ (1 – 5 %) | 44,10 € |
Example of calculation with round assumptions. Discount and discount are calculated from the price on which they are granted; therefore divided by (1 – rate) and not multiplied by (1 + rate).
For drawing requests, Pro creates this calculation fully automatically as a design with work schedule, times, costs and seasons; each value shows its origin, and you release the design. Pro is unlocked on request. The page describes how this takes place Full automatic calculation from drawing and CAD. For a lot size with contract manufacturing example see Calculation in contract manufacturing.
A price is only as resilient as its assumptions
The precalculation makes every cost block visible. STEP geometry, drawing requirements, working sequence, machine profile, procurement and commercial conditions must fit together for a releaseable offer.
Questions and answers
How do you calculate a CNC offer?
First, the cutting volume is translated into peak time via the realistic removal performance. In addition, incidental time, material, tools, quality, external performance, set-up and one-off costs.
Why is the material removal rate input?
Machining volume and achievable time machining volume make the machine time understandable. The degree of use takes into account that the theoretical removal performance is not achieved permanently by means of access and exit routes, deliveries and tool changes.
What is one of the one-off costs?
Typical one-off costs are CAM programming, device planning, testing planning and documentation. In the computer, they are divided by the batch size so that their share per part remains visible.
How does cost price and offer price differ?
The cost price covers individual and overhead costs. The offer price also includes the desired margin. Discount, discount, risk or sales conditions may have to be taken into account separately.
What is an offer calculation?
The quotation calculation is the pre-calculation before acceptance of the order: It determines the price of material, production times, one-off costs and surcharges offered by an enterprise. It usually follows the scheme of the surcharge calculation from the individual costs to the production and cost to the list price with discount and discount.
Is that an offer configurator?
No. An offer or product configurator compiles variants of its own product from defined options and specifies their price. The offer calculation here calculates the price of a drawing part, which is different every time, from times, material and sets. For many drawing requests, Pro creates this calculation fully automatically as a design, which you release.
Can the computer generate a binding offer?
No. It provides a transparent precalculation. Drawing tolerances, testing effort, coating, delivery date, minimum quantities, material certificates and operational rules must be supplemented and released.