Wire EDM main cut time formula
Multiply the wire path length in millimetres by the cut height of the workpiece. Divide the resulting area by the area cutting rate in mm²/min. For multiple contours, add the cutting times and count each start.
The app uses starting values by material class and height range. Your machine's technology table can give more precise values for the wire and cutting programme.
Main cut time = contour length × cut height ÷ area cutting rate
Example for a contour in hardened steel
A 420 mm contour passes through a 40 mm thick workpiece. At an assumed area cutting rate of 100 mm²/min, the 16,800 mm² cut takes 168.0 min for the main cut.
For IT7 and Ra 0.8 µm, allow one trim cut at 35 percent of the main cut time. Add 0.7 min for threading and 3.0 min for alignment to get a cycle time of 230.5 min. The example uses a loading and unloading time of 0 min.
Time components in wire EDM
| Time share | Calculating path | Time |
|---|---|---|
| Main cut | 420 × 40 ÷ 100 | 168.0 min |
| Trim cut | 168,0 × 0,35 | 58.8 min |
| Threading and alignment | 0,7 + 3,0 | 3.7 min |
| Time of piece | 168,0 + 58,8 + 3,7 | 230.5 min |
First-cut inspection and setup are batch times. The app shows programming time separately.
Closed contours and trim cuts
A closed internal contour needs a starting hole for the wire. Plan it early in the work plan, for example before hardening. Estimate starting holes, wire threading and the trim cuts for each contour as separate steps.
Tighter tolerances and finer finishes can require additional trim cuts. Check the cutting rate and sequence for your machine and wire before using the estimated time in a quote.
Sources and classification
- Wire EDM time in the CNC Kalkulator app
Formula, example inputs and starting values for estimating.
Questions and answers
How do I convert the area cutting rate to a feed rate?
Divide the area cutting rate in mm²/min by the cut height in mm. At 100 mm²/min and 40 mm height, the calculated wire feed along the contour is 2.5 mm/min.
What makes up the batch time in wire EDM?
Multiply cycle time by the quantity and add first-cut inspection and setup. The app lists programming time separately.