Employee machining and simultaneous movement
The workpiece is positioned spatially between operations during the machining process. Simultaneous machining moves several axes together during the cutting process. For the calculation, it is determined which task is actually required and which machine it can perform.
Accessibility, tool length, clamping agents and collision check are part of the technical planning. The free milling time calculator evaluates entered paths and projections; it does not simulate five-axis kinetics.
Weighing less stresses against machine costs
A part can cost more on a machine per productive hour and still require less set-up, subtracting or handling time. Both variants are therefore compared over the whole lot. Program creation, device and initial sample testing remain their own parts.
Example of two production variants
Variant A requires 40 minutes of set-up and 18 minutes per part at 70 €/h. Ten parts cost 256,67 € time. Variant B requires 60 minutes set-up and 12 minutes per part at 110 €/h: 330 €.
For 100 parts, the time costs are 2,146.67 € for A and 2,310 € for B. In this example, the shorter unit time of B is not sufficient to compensate for the higher hourly rate. The example compares only the mentioned time costs; indeed, different programming, tooling and testing costs are added.
K_Los = (t_Rüst + N × t_Stück) × hourly rate < 60
Prove time assumptions intelligible
For freely shaped surfaces and simultaneous movements, a CAM time approach or measured reference programs are often more meaningful than a pure path/feed calculation. These approaches must also take appropriate account of acceleration, control, tool changes and operational downtimes.
Questions and answers
Is 5-axle milling always more expensive?
No. Total costs depend on setups, programming, machine time, handling and cost. The same scope of delivery is compared with the same quantity.
Does the free app calculate collision-free 5-axis tool paths?
No. It calculates times and costs from input assumptions. Tool paths and collision clearance remain tasks of manufacturing planning and CAM system.